Do You Know How To Installation Flexible Aluminum Foil Duct?

Do You Know How To Installation Flexible Aluminum Foil Duct?

Flexible Aluminum Foil Duct Installation:

1)    Install Aeroduct as straight as possible with an allowable sag of only 50mm between each distance of 1 meter
2)    All bends should be made as large as possible and should have a radius of not less than the diameter of the duct in use  "U" shape bends should be avoided. However, if unavoidable, make sure that the distance between the centre point of the duct is at least 2 times the diameter of the duct in use.

3)    Use metal or galvanized iron hanger that is at least 25 mm wide and should support the flexible duct with at least half the circumference surface in contact,
4)    Do not connect Aeroduct to connector with sharp ends. An allowance of at least 2 rounds of flexible ducts should be provided at point of joining before wrapping the connections with 2' wide aluminium or duct tape. Clamp tightly, with plastic or metal clamps followed by another layer of aluminium tape to prevent tearing
5)    Extra care must be taken when making connections to fixed conventional duct. An additional hanging support is always recommended. If Aeroduct is installed vertically, the use of hanging support by wre for every distance of 1.5 meter is necessary,
6)    Connections to any other types of air supplying component should have as little bending as possible.